
Tel: 01455 617139 Fax: 01455 617140

News
Please select a news article from below to read the full story
21/07/2008 | Below-ground suds. The preferred drainage solution for military barracks redevelopment. (Stormwater Management Ltd)
The North East of England is home to one of the British Army's largest Barracks with a military and civilian population of over 12000. As part of a long term modernisation and expansion programme of the site, contractors have installed an innovative below-ground, SUDs [Sustainable Urban Drainage] solution to accommodate surface-water run-off for a total of 9400sqm car parking area. In periods of heavy rainfall, surface water run-off from large areas of impermeable paving can overwhelm drainage systems, leading to flooding. In view of this, groundworks contractor, K Rouse Ltd, chose a combination of conventional channel drainage, feeding into below-ground attenuation tanking designed and installed by SUDS specialists, Stormwater Management Ltd. The purpose of an attenuation tank is to accept and retain surface water run-off during periods of high intensity rainfall, then manage its discharge into the drainage system at a controlled rate. At the site, Stormwater Management designed a 576m³ capacity system comprising 2880 of its FlowBlock modular water storage cells. FlowBlock cells are high strength, lightweight polypropylene units, 1.0x0.5x0.4m with a 95% void ratio. Their modular format allows them to be linked together to form large underground tanks of virtually any predetermined configuration. FlowBlock assemblies are wrapped in either a geotextile or a geomembrane depending on their application and connected to the drainage system. On site, Stormwater Management installed two tanks 40mx10mx0.8m and 40mx8mx0.8m beneath a car park serving the Barracks. The tank dimensions were calculated using the company's in-house drainage design software, which is based on the industry standard Wallingford Procedure. Both tanks were excavated to a depth of 2m deep, graded to line and level, and lined with 1mm thick VFPE impermeable geomembrane. FlowBlock cells were then installed by hand and wrapped in the geomembrane to create a completely sealed system with mechanically welded seams. Flow regulators were installed at the outlet so that discharge rates could be managed to the pre-determined levels. On completion, the attenuation tank was overlaid with a layer of compacted Mot Type 1, and selected as-dug material with a black top wearing and base course, giving a total construction cover of 1200mm. Surface water drainage was achieved through a network of linear drainage channels. The Barracks SUD system was installed in early summer 2007 and has performed as specified over its first full year of use. For more information on Stormwater Management Ltd , products and services contact Tel: 01455 502222 Email: sales@storm-water.co.uk

30/06/2008 | Are You Arb Enough..!
Geosynthetics sponsored two teams entered by Ravencroft Arboricultural Services for this years Arborist Team Challenge. Held in Cirencester at the Arboricultural Trade Fair, the 3ATC consisted of six trials testing both the team’s arboricultural knowledge and physical ability. Work/Climb Log shift Chainsaw bar change Site Safety Kit Inspection Tree Fungi identification Eight two staff teams represented their companies in this years challenge. Throughout the day the leaders jostled for position as each trial was completed. Ravencroft team Alex Laver and Robert Bell came in 2nd place beaten only by some tree fungi. Whilst Devon Tree Services took first place this year. Better luck next year..! Despite the gruelling competition you will be happy to know all competitors went home with a goody bag including an Arboricultural Association mug, Stein Safety Glasses and a commemorative "I was Arb enough!" T Shirt. Geosynthetics: Roy Partington and Amy Norcliffe together with Ravencroft team members
02/06/2008 | Telegrid reinforced embankment in 'Tip-Top Condition'
An observational approach proved to be a good solution for an embankment at the former tip in the West Midlands. A 4.2ha parcel of elevated land situated just of the A444 (Phoenix Way) on the outskirts of Coventry, West Midlands, was for many years regarded as being uneconomical to develop. A former tip, the site comprised a narrow, elongated mound of made ground – placed there during construction of the A444 – increasing by up to 14m above the surrounding areas. The land was considered unsuitable for economic development because of the perceived need to remove substantial quantities of spoil, with its associated high costs and environmental impact. Client Wigley’s proposed to develop the land for commercial use, including a new operational command unit for the West Midlands Police. This required the transformation of the shallow-sloped mound into a relatively level development platform. The earthworks contractor for the development was Trelanmex, with consultant Joynes Pike and Associates (JPA) acting as designers to Trelanmex. Solution Two key development criteria were sustainability and this issue of the made ground, which had to be dealt with and not just moved from one are to another. This meant that the least amount of material removed from the site was the most desirable outcome for all parties. It presented JPA and Trelanmex with the challenge of incorporating the existing made ground, cost-effectively, within the site boundary. The proposal involved a split-level development with flat benches at 7m and 14m above surrounding areas. Bordered by a dual carriageway to the east and Coventry canal to the west led to slopes averaging between 45° and 50°. This raised issues over their long-term stability. A scheme design identified that reinforced soil slopes would comprise the most economical solution. Design Because of the tight time schedule JPS has less that a week to produce a satisfactory reinforced soil slope design, which also required approval from a British Waterways engineer. This meant that there was little scope for any site investigation and soil shear strength testing. To progress the works and achieve cost-effective design, the following strategy was adopted. Ground conditions were taken from an existing phase-two geo-environmental assessment, which had identified up to a 14m depth of made ground, underlain by firm to stiff sandy gravelly clay of glacial till over very weak sandstone of the barren measures of the upper coal measure. The made ground was identified as comprising materials associated with the site’s use as a landfill for inert materials. They were typically highly variable, broadly classifiable as a soft to firm gravelly clay, becoming increasingly granular with depth. In spite of its variable nature the made ground was classified as predominantly suitable material for earthworks – category 2C, with the exception of some oversize concrete boulders and occasional wood, metal and glass – having neutral pH and low sulphate. A site visit by a JPA engineer allowed trial pitting to generally confirm the reported characteristics of the made ground. After discussion with Trelanmex, it was agreed that during excavation for the wall installation, where necessary the material would be screened to remove unsuitable material. This allowed JPA to assess design values for the shear strength of the made ground, based on the average plasticity index of clay component within it and well-published relationships with its critical state internal angle of friction. A key requirement was for the material’s validation by an engineer during the works – an observational approach to the design. The sections were designed to satisfy global and external stability for a 60 year design life in accordance with BS8006:1995 and to the principles of BS EN ISO 14475:2006. The resulting design led to the requirement for over 56,900m² of geogrid, with uniaxial ultimate tensile capacities ranging from 20kN to 100kN. The geogrids selected where from the Telegrid range produced by Teletextiles and distributed in the United Kingdom by Geosynthetics Limited. Construction The construction of the 490 linear metres, 7m to 14m high reinforced soil slope was conducted over an 18-week working period from September 2007 to February 2008, (including a break over the winter months). The installation involved excavation the existing mound to the surrounding ground level and then the basal 450mm of fill to be excavated and re-compacted in engineered layers for the footprint of the reinforced soil slope. This subterranean re-compaction was important, given that rock-head was between 1m to 2m below the slope founding level; the design had identified that this was necessary to increase shear strength. It would also provide an adequate factor of safety on three-part wedge failure mechanisms undercutting the reinforce soil slope, which were identified as a critical global stability issue at design stage. The philosophy behind the material selection was based on the Observational Method, advocated in Eurocode 7. Provided the proposed methodology and the design requirements could be satisfied, and perishable substances had been adequately screened out of the materials, it would then be validated for use by a JPA engineer. Occasional lenses of soft cohesive fill were identified during the excavations and given the potential for mattressing and inadequate drained shear strength were segregated from the works and used for landscaping. The Observational Method used by the design team was not simply a method of observing the construction. Clear criteria had to be met and a number of alarm levels adhered to where some materials might not have been suitable for use in a particular area. A methodology was also required to deal with these materials. Everything that could be reasonable foreseen had to be taken into account and procedures put in place to deal with them. An additional consideration within the screening approach was the section of salient boulders for incorporation into landscaping features, an aspect specifically requested by the project architect to reflect the site’s history. For the slope construction JPA and Trelanmex negated the requirement to use formwork or a wraparound geogrid facing by overfilling the compacted backfill and trimming the profile back to the leading edge of the geogrids. Given that the long-term stability of the exposed face would lead to slumping / minor face instabilities, the design included a 2m length mid layer geogrid to prevent excessive material loss at the face. A topsoil retention system with hydro-seeding to provide a green and cohesive resistance at the face for long-term aesthetics will also be installed as the development progresses. Conclusion This project demonstrated that through innovative design and cooperation between engineer and contractor, a sustainable, cost effective design carried out by an observational approach can be used where limited time is available for laboratory testing. Last, but not least, this £500,000 project demonstrated the transformation of an unsightly former tip into a valuable commodity.
News

Contractors Norwest Holst & Deacon Landscapes install DeepRoot Silva Cell system at the new Waitrose supermarket in Winchester.
Geosynthetics Limited
Fleming Road Harrowbrook Ind Est
Hinckley Leicestershire LE10 3DU
Tel: 01455 617139 Fax: 01455 617140
